The Mascot, Avenue, Bonbeach Level Crossing closed in February 2020 during a two-week construction-blitz that saw the opening of the new direct connection from McLeod Road to Nepean Highway, trains running on the new rail bridge, and stopping at the new Carrum Station.

During early community consultation for the Carrum Level Crossing Removal Project we heard that locals wanted Station Street connected across Patterson River.

A new road bridge was added to the scope of works and opened to traffic in September 2018, creating a more direct road network and enabling the closure of the Mascot Avenue, Bonbeach level crossing.

Works will continue throughout 2020 to complete the new Carrum Station and create four new community open spaces as part of Carrum’s $50 million revitalisation.

On behalf of the Victorian Government, the Level Crossing Removal Project is overseeing the removal of 75 dangerous and congested level crossings across Melbourne by 2025.

Current disruptions

23 Mar 2020 1584882000 1591019940 to Jun 2020

Old Post Office Lane, Carrum – road closure

Road; Pedestrian

Icon/Road/Rev Road

Icon/Ped/Rev Created with Sketch. Pedestrian

FRANKSTON LINE

Old Post Office Lane is closed to pedestrians and traffic from Monday 23 March to mid 2020.

30 Mar 2020 1585486800 1586959140 to Apr 2020

Station Street, Bonbeach – lane closure

Road

Icon/Road/Rev Road

FRANKSTON LINE

From Monday 30 March to mid April, Station Street, Bonbeach will be reduced to one lane between Mernda Avenue, Bonbeach and Karrum Karrum Bridge.

20 Apr 2020 1587304800 1589810340 to 18 May 2020

Nepean Highway, Carrum – lane and parking closures

Road; Pedestrian; Cycling

Icon/Road/Rev Road

Icon/Ped/Rev Created with Sketch. Pedestrian

FRANKSTON LINE

Nepean Highway will be reduced to two lanes from Monday 20 April to Monday 18 May. There will also be no on-street car parking along Nepean Highway from Stephens Street to Progress Avenue.

21 Apr 2020 1587391200 1587736740 to 24 Apr 2020

Mascot Avenue, Bonbeach – road closure

Road

Icon/Road/Rev Road

FRANKSTON LINE

Mascot Avenue, Bonbeach will be closed at Station Street from Tuesday 21 April to Friday 24 April.

News

34 crossings gone as new station opens in boom gate free Carrum

34 crossings gone as new station opens in boom gate free Carrum

17 Feb 2020
Traffic transformation in Carrum with McLeod Road open

Traffic transformation in Carrum with McLeod Road open

11 Feb 2020

Featured video

Image gallery

Publications

Southern Program Alliance Policies

05 Mar 2020

Safety, cultural diversity, procurement and quality policies of the Southern Program Alliance.

Carrum community update – December 2019

27 Dec 2019

Footpath upgrades on Station Street are now complete and landscaping works are underway. New on-street car parking for safe and easy access to local shops is back for summer.