The Straddle Carrier Journey

16 Apr 2018

Video

Transcript

Visions:

  1. Time lapse photography of gantry cranes being built during day and night works April 2017
  2. Straddle Carrier assembled July 2017 - day time visions of straddle carrier
  3. Support beams installed August 2017 - night works of beams being installed
  4. Straddle carrier lifted August 2017 - view of straddle carrier in position
  5. First span placed August 2017 - time lapse of night works showing first span being placed
  6. Murrumbeena Road September 2017 - time lapse of night works showing span being placed
  7. Koornang Road November 2017 - time lapse day and night works showing span being placed
  8. Grange Road February 2018 - time lapse of day works showing span being placed
  9. Poath Road March 2018 - time lapse of night and day works showing span being placed
  10. Straddle carrier removed April 2018 - time lapse of straddle carrier being removed and placed on ground
  11. 180 days of operation - time lapse of construction works
  12. 174 beams installed - time lapse of construction works
  13. 150,000 worker hours - time lapse of construction works
  14. 60,000 tonnes of concrete and steel installed - time lapse of night works
  15. Every level crossing between Caulfield and Dandenong gone by the end of the year - time lapse of construction.