Thanks for your patience during the Hurstbridge line blitz

16 May 2018

Video

Transcript

The Hurstbridge line blitz

[Vision:  Aerial view of construction in progress - time lapse of construction]

THANK YOU FOR GETTING THROUGH OUR LONGEST RAIL SHUTDOWN EVER

[Vision:  Aerial view of the Hurstbridge line under construction - staff working on construction]

THE HURSTBRIDGE LINE BLITZ

[Vision:  Time lapse of bus arriving and commuters]

750,000 TRIPS ON REPLACEMENT BUSES

[Vision:  View of inside bus]

WE APPRECIATE IT TOOK EXTRA TIME

Female staff member

Thanks for your patience.

Three male staff members

Thanks for your patience.

Male staff member 1

Thank you for your patience.

Male staff member 2

From everyone at the Level Crossing Removal Authority … thanks for your patience.

[Vision:  Time lapse of night and day works on construction - and new Rosanna Station and train]

WHILE YOU WERE ON THE BUS WE EXCAVATED 30,000 CUBIC METRES OF SOIL, INSTALLED BRIDGES, DUPLICATED TRACKS AND BUILT A NEW ROSANNA STATION

Female passenger 1

I didn’t expect the station to be this big.

Male passenger

Now it actually looks a lot more modern.

Female passenger 2

I think it’s going to help a lot with traffic congestion and getting us to and from the city a lot more efficiently.

[Vision:  Time lapse visions of trains moving freely - aerial view of less congested roads

WE HOPE YOU’RE ENJOYING YOUR UPGRADED HURSTBRIDGE LINE, LESS CONGESTED ROADS AND A SAFER COMMUNITY

[LEVEL CROSSING REMOVAL AUTHORITY]

[VICTORIA’S BIG BUILD - VICTORIA State Government]

[Speaker:  Authorised by Victorian Government, 1 Treasury Place, Melbourne]

Was this page helpful?
Send feedback

Contact Us

1800 105 105

Get in touch with us for any queries you have about our projects

24 hours, 7 days