31 August 2020

Updated 23 April 2024


Publication of the Groundwater Monitoring and Management Plan and Edithvale Wetlands Monitoring and Mitigation Plan is a requirement for this project under the Environment Protection and Biodiversity Conservation Act 1999 (EPBC Act) and Planning and Environment Act 1987 (P and E Act).

Two level crossings (Edithvale Road, Edithvale and Bondi Road, Bonbeach) have been removed by lowering the rail line into trenches.

In March 2017, the Minister for Planning determined an Environmental Effects Statement (EES) was required for the Projects to assess potential impacts to groundwater levels, groundwater quality and the Edithvale-Seaford Wetlands.

A requirement of the EES was the development of an Environmental Management Framework (EMF) which included specific Environmental Performance Requirements (EPRs) for the project.

Due to the proximity of the projects to the Edithvale Wetland, which is one of 2 wetlands that form the Edithvale Seaford Wetlands Ramsar Site, the projects also required approval under the EPBC Act. Approval 2017/7906 was granted for the projects under sections 130(1) and 133(1) of the EPBC Act by the then Commonwealth Department of Agriculture, Water and Environment, now the Department of Climate Change, Energy, the Environment and Water (DCCEEW), on 3 December 2018.

Importantly, the EES identified that groundwater levels and quality could be maintained for the Edithvale and Bonbeach Projects within acceptable thresholds through engineering controls and implementation of the EPRs.

As such, LXRP prepared 2 plans;

In summary, the purpose of the Groundwater Monitoring and Management Plan is to ensure that the existing groundwater conditions (quality and levels) are not adversely affected by the project.

The purpose of the Edithvale Wetlands Monitoring and Mitigation Plan is to identify whether groundwater mounding (as a result of the project) reaches Edithvale Wetland and whether this groundwater increase affects the suitability of the habitat and therefore use of the wetland by birds.

It also identifies mitigation measures to be implemented if an impact is detected at Edithvale Wetland that is attributable to the level crossing removal project.

The Groundwater Monitoring and Management Plan and Edithvale Wetlands Monitoring and Mitigation Plan were originally approved by the Australian Minister for the Environment on 2 December 2019.

The Groundwater Monitoring and Management Plan and Edithvale Wetlands Monitoring and Mitigation Plans were revised to account for design changes. The Australian Minister for the Environment accepted these changes on 3 July 2020.

There have since been a further 3 revisions to the Groundwater Monitoring and Management Plan as follows:

  • Revision to account for groundwater monitoring changes. The Australian Minister for the Environment accepted these changes on 26 August 2020.
  • Revision to account for groundwater monitoring changes. The Australian Minister for the Environment accepted these changes on 4 January 2022.
  • Revision to reduce extent of groundwater monitoring, given monitoring undertaken since October 2020 has shown no unreasonable project-induced impacts. The Australian Minister for the Environment accepted these changes on 8 January 2024.

Annual Compliance Report

The approval under the EPBC Act requires us to publish an Annual Compliance Report for each 12 month period following the project’s commencement.

Please note the Annual Compliance Reports relate only to the EPBC Act approval.

Annual Compliance Report – No. 1

Accordingly, the Annual Compliance Report No.1 has been prepared for the reporting period between 13 October 2020 and 12 October 2021.

The Annual Compliance Report shows the project was compliant with all conditions specific to the project during the reporting period.

Annual Compliance Report – No. 2

The Annual Compliance Report No. 2 has been prepared for the reporting period between 13 October 2021 and 12 October 2022.

The Annual Compliance Report shows the project was compliant with all conditions specific to the project during the reporting period.

Annual Compliance Report – No. 3

The Annual Compliance Report No. 3 has been prepared for the reporting period between 13 October 2022 and 12 October 2023.

The Annual Compliance Report shows the project was compliant with all conditions specific to the project during the reporting period.


Independent Audit Reports

The approval under the EPBC Act also requires us to undertake Independent Audits of compliance with the approval conditions at specified times. The Independent Audits only relate to the EPBC Act approval.

The Independent Audit for the first year of the EPBC Act approval (being October 2020 to October 2021) has been completed. The Independent Audit has been submitted to and approved by DCCEEW.

The next Independent Audit for the time period October 2021 to October 2023 is currently underway and will be published on this webpage in due course.


If you require assistance in accessing or understanding these documents, please contact us by emailing contact@levelcrossings.vic.gov.au