Caulfield to Dandenong area 3 Community update – October 2017

01 Oct 2017

Major works are underway to remove level crossings at Corrigan, Heatherton and Chandler roads and rebuild Noble Park station.

Getting it done

We’ve been very busy over the past month and have made some great progress at Noble Park. You would have noticed that we have installed beams over Heatherton, Corrigan and Chandler Roads, another step in the removal of these dangerous and congested level crossings.

The progress has not stopped there, we have now completed the installation of not only the Super T Beams, but also parapets, which will act as barriers along the elevated rail. We have also rebuilt the rail bridge over Mile Creek and continued construction of the retaining walls for the new embankment. Over the next month you will see us continuing with the installation of the new track on the elevated rail. We will also continue construction of the canopies, as well as concrete pouring.

New Noble Park Station

We’re progressing with the construction of Noble Park Station with the completion of the hollow core deck, which will form the base of the station platform. We’re now installing the canopynover the deck, and the new station is steadily taking shape.

Project timeline

  
October 2016

Piling (ground strengthening) commenced

December 2016

Noble Park Station Design Release

February 2017

Fist piers installed

April 2017

First beams installed

June 2017

Piling completed

July 2017
  • Beams installed over Corrigan Road
  • Installation of parapets commenced
September 2017
  • All piers installed
  • Construction on Noble Park Station
  • Platform commenced
  • Beams installed over Heatherton and Chandler Roads
October 2017
  • All beams installed
  • Bridge deck over Mile Creek rebuilt
  • Installation of Noble Park platform completed
November – December 2017

Embankment construction to commence

Early – mid 2018
  • Commence laying of elevated track
  • Rail signalling commences installation
  • Noble Park Station opened
Mid – late 2018
  • Tack and signalling complete
  • Open space landscaping complete
  • Bicycle and pedestrian path complete

Disruptions

We’re working hard to minimise disruptions for residents, commuters, local businesses and shoppers wherever possible. However, there will be some disruptions including the following:

  • Buses will replace trains between Caulfield and Dandenong from 12:30am Saturday 18 November until the last service on Sunday 19 November 2017.
  • Buses will also replace trains between Caulfield and Dandenong after 8:00pm on selected nights throughout November.

We appreciate your patience while we continue this important project to remove these dangerous and congested level crossings.

View this is PDF version PDF, 320.7 KB

Was this page helpful?
Send feedback

SMS updates

Receive SMS on the progress of the Level Crossing Removal Project

Sign up for SMS updates

Updates

Stay up to date with the progress of the Level Crossing Removal Project

Sign up for updates

Contact Us

1800 105 105

Get in touch with us for any queries you have about our projects

24 hours, 7 days