Caulfield to Dandenong area 3 Community update – November 2017

01 Nov 2017

Corrigan/Heatherton/Chandler Roads

Major works are underway to remove level crossings at Corrigan, Heatherton and Chandler roads and rebuild Noble Park station.

What we’ve been doing

We’re continuing to meet major milestones at Noble Park. We’ve completed the installation of barriers along the elevated structure and have laid the first piece of track.

New Noble Park Station

Construction of the new Noble Park Station is well underway. We’ve put the finishing touches on the hollow core deck, installed the new station’s escalators and the first segments of the station canopy.

Over the coming months we’ll complete the installation of the station canopy and install the new station’s lifts. We’ll also start the construction of the new station building and begin cladding.

Disruptions

We’re working hard to minimise disruptions for residents, commuters, local businesses and shoppers wherever possible. However, there will be some disruptions including the following:

Road

Until February 2018, Mons Parade will close intermittently between Heatherton Road and Ian Street, from 7:00am to 6:00pm daily. On-street car parking on Ian Street may be affected at times. Traffic will detour via Ian Street.

Rail

Buses will replace trains between Caulfield and Dandenong from 12.30am Saturday 9 December until the last service on Sunday 10 December.

Buses will replace trains between Oakleigh and Dandenong from 12:30am Saturday 16 December until the last service on Sunday 17 December.

We appreciate your patience while we continue this important project to remove these dangerous and congested level crossings.

Project Timeline

DateStage
Oct 2016

Piling (ground strengthening) commenced

Dec 2016

Noble Park Station Design Release

Feb 2017

Fist piers installed

April 2017

First beams installed

June 2017

Piling completed

July 2017
  • Beams installed over Corrigan Road
  • Installation of parapets commenced
Sept 2017
  • All piers installed
  • Construction on Noble Park Station Platform commenced
  • Beams installed over Heatherton and Chandler Roads
Oct 2017
  • 100% of beams installed
  • Bridge deck over Mile Creek rebuilt
  • Installation of Noble Park platform completed
Nov - Dec 2017

Embankment construction to commence

Early - mid 2018
  • Commence laying of elevated track
  • Rail signalling commence installation
  • Noble Park Station Operational
Mid - late 2018
  • Track and signalling complete
  • Open space landscaping complete
  • Bicycle and pedestrian path complete

View this as a PDF, 320.4 KB