Caulfield to Dandenong area 2 Community update – November 2017

01 Nov 2017

Clayton/Centre

Major works are underway to remove level crossings at Clayton and Centre roads and rebuild Clayton station.

What we’ve been doing

We’ re continuing to meet major milestones in Clayton. Our biggest accomplishment last month was completing the installation of super T beams. This was no small task,
with a total of 172 beams installed. We’ve also installed the remaining barriers along the elevated structure.

New Clayton Station

Construction of the new Clayton Station is well underway. We’ve completed the hollow core deck and have begun ground level station preparation works including the foundation works for station lifts, staircases and escalators. Next month we’ll continue the ground level preparation works for the new station facilities. We' will also start to remove scaffolding at the site now that the hollow core deck and the installation of barrier is complete.

Disruptions

We’re working hard to minimise disruptions for residents, commuters, local businesses and shoppers wherever possible. However, there will be some disruptions
including the following:

Road

The following traffic changes will occur at Clayton Road, Clayton from 10:30pm to 7:30am on the following nights:

  • Wednesday 29 November 2017 (southbound closure only)
  • Friday 1 December 2017 southbound closure only)
  • Tuesday 5 December 2017 (full closure).

While works are carried out for the elevated structure, please follow detours in place via Princes Highway, Westall Road, Centre Road, Carinish Road and Haughton Road.
Centre Road, Clayton, will close at the level crossing from 10:00pm to 6:00am
on the following nights:

  • Saturday 9 December 2017
  • Sunday 10 December 2017
  • Wednesday 13 December 2017.

Please detour via Clayton Road and Westall Road.

From mid-September to March 2018, Carinish Road will close intermittently to rebuild Clayton Station. Detour via Centre Road and Clayton Road.

Rail

Buses will replace trains between Caulfield and Dandenong from 12:30am Saturday 9 December until the last service on Sunday 10 December. Buses will replace trains between Oakleigh and Dandenong from 12:30am Saturday 16 December until the last service on Sunday 17 December. We appreciate your patience while we continue this important project to remove these dangerous and congested level crossings.

Project Timeline

DateStage
October 2016
  • Piling (ground strengthening)commenced
  • Removal of Clayton Station
April 2017
  • First piers installed
  • First beams installed
June 2017
  • Piling completed
  • Clayton Station design released
July 2017
  • Twin track piers installed at Centre Road
  • Haunches installed
August 2017
  • Installation of parapets commenced
  • Beams installed over Clayton Road
September 2017
  • Construction on Clayton
  • Station Platform commenced
October 2017
  • All piers installed
  • Beams installed over Centre Road
November 2017 100 per cent of beams installed
December 2017 Embankment construction
Early - mid 2018
  • Commence laying of elevated track
  • Rail signalling commences installation
Mid - late 2018
  • Clayton Station open
  • Track and signalling complete
  • Open space landscaping complete
  • Bicycle and pedestrian
  • Path complete

View this in PDF form PDF, 283.7 KB

Was this page helpful?
Send feedback

SMS updates

Receive SMS on the progress of the Level Crossing Removal Project

Sign up for SMS updates

Updates

Stay up to date with the progress of the Level Crossing Removal Project

Sign up for updates

Contact Us

1800 105 105

Get in touch with us for any queries you have about our projects

24 hours, 7 days