16 Jan 2018

Major works are underway to remove dangerous level crossings at Corrigan, Heatherton and Chandler roads and build a brand-new station in Noble Park.

Works ramping up

We hit a major milestone in Noble Park recently with the installation of the new station canopy. A total of 59 pieces were placed individually to provide a unique covering over the station platform.

We have also installed a massive 2,400 linear metres of plinth track. A rail plinth is a concrete block that will secure the rail line. The remaining 400 linear metres of plinth track, which will run through Noble Park Station, will be installed in early 2018.

Steel framing for the new station canopy at Noble Park Station

Brand-new Noble Park Station

Construction of the new Noble Park Station is almost complete. We have installed the first walkways along the elevated structure and have made significant progress constructing the ground level station building.

Over the next month, you will notice a lot of activity in the area as we complete the new station, lay the final pieces of rail track, and begin overhead wiring on the elevated structure.

Following this work we will remove the boom gates for good at Heatherton, Corrigan and Chandler roads and open the new Noble Park station.

Project timeline

DatePhase
October 2016 Foundation works to strengthen the ground commenced
December 2016 Noble Park Station design released
February 2017

First piers installed

April 2017

First beams installed

June 2017

Foundation works completed

July 2017

Beams installed over Corrigan Road

Installation of parapets commenced

September 2017

All piers installed

Construction on Noble Park Station platform commenced

Beams installed over Heatherton and Chandler Roads

October 2017

100 per cent of beams installed

Bridge deck over Mile Creek rebuilt

Installation of Noble Park platform completed

November to December 2017

Embankment construction commenced

Commence laying of elevated track

Early to mid-2018

Commence installation of rail signalling

Noble Park Station operational

Level crossings removed at Corrigan, Heatherton and Chandler roads

Track and signalling complete

Mid to late 2018

Open space landscaping complete

Bicycle and pedestrian path complete

Disruptions

We’re working hard to minimise disruptions for residents, commuters and local businesses wherever possible. However, there will be some upcoming disruptions including the following:

Road

Heatherton Road, Noble Park, will close at the level crossing from 10:00pm to 7:00am on the following nights:

  • Friday 12 January 2018
  • Saturday 13 January 2018
  • Sunday 14 January 2018.

Please follow detours in place via Kelvinside Road, Corrigan Road, Chandler Road and Douglas Street. Chandler Road, Noble Park, will close at the level crossing from 10:00pm to 6:00am on the following nights:

  • Tuesday 16 January 2018
  • Wednesday 17 January 2018.

Please follow detours in place via Heatherton Road, Douglas Street and Yarraman Road.

Until February 2018, Mons Parade will close intermittently on selected days and nights between Heatherton Road and Ian Street. This closure will enable further works on the new Noble Park station. On-street car parking on Ian Street may be affected at times. Traffic will detour via Ian Street.

Rail

Buses will replace trains between Caulfield and Dandenong from Wednesday 10 January until the last service on Wednesday 17 January 2018.

Buses will replace trains between Oakleigh and Dandenong from 8:00pm until the last service each night from Sunday 21 January to Wednesday 24 January 2018.

Buses will replace trains between Caulfield and Dandenong from 8:00pm until the last service on Thursday 25 January 2018.

Buses will replace trains between Westall and Dandenong from Tuesday 30 January until the last service on Sunday 11 February 2018. Train services will resume on Monday 12 February 2018.

We appreciate your patience while we continue this important project to remove three dangerous and congested level crossings in Noble Park for good.

View the PDF print version of this community update PDF, 304.7 KB

Was this page helpful?
Send feedback

Contact Us

1800 105 105

Get in touch with us for any queries you have about our projects

24 hours, 7 days