Caulfield to Dandenong Area 2 Community Update – March 2018

01 Mar 2018

Image: View of the new Clayton Station from Carinish Road, Clayton

Crossings gone by mid-April

We’ve been ramping up work in Clayton to get ready for the removal of the two dangerous and congested level crossings in Clayton, and open the new Clayton Station by mid April.

We've finished installing track through the station area, and are also making great progress on rebuilding Clayton Station. We have continued paving works on the new station platform and installed more pieces of canopy, including the roof sections which will cover the new platform.

The station lifts will be installed along with the final pieces of the station canopy to get ready for the new station being operational in April.

From Friday 30 March, the team will launch into a 17-day construction blitz which will see two level crossings removed at Clayton and Centre roads, and the brand new Clayton Station open to the public.

Major works are underway to remove level crossings at Centre and Clayton roads and rebuild Clayton Station by the end of this year.

Image: Our Info Hub in Clayton

Info Hub

Earlier this month we opened the Clayton Information Hub.

The hub offers the community the chance to talk to our staff, grab extra information, and ask any questions they have about the project.

The hub opening hours are:

  • Monday 9:00am to 5:00pm
  • Wednesday 9:00am to 5:00pm
  • Every second Saturday 9:00am to 12 noon

Image: Clayton Station taking shape

Upcoming disruptions

We’re working hard to minimise disruptions for residents, commuters, local businesses and shoppers wherever possible.

However, there will be some disruptions including the following:

Road

Carinish Road, Clayton

  • Until mid-April 2018, Carinish Road will close intermittently from Kanooka Grove towards Clayton Road to rebuild Clayton Station. Please detour via Centre Road, Browns Road and Clayton Road. Local residential access will be maintained.

Clayton Road, Clayton

  • Centre Road, Clayton, will be closed at the level crossing from 10:00pm to 6:00am each night on Sunday 25 March 2018 and Monday 26 March 2018. Minor delays can be expected. Please detour via Detour via Clayton Road, Fairbank Road and Westall Road.

Rail

  • Buses will replace trains between Caulfield and Westall from 8:00pm until the last service each night from Monday 26 March to Thursday 29 March 2018.
  • Buses will replace trains between Oakleigh and Dandenong from 12:30am Friday 30 March until the last service on Monday 2 April 2018.
  • Buses will replace trains between Caulfield and Westall from the first service Tuesday 3 April until the last service on Sunday 15 April 2018.

Victoria's Big Build

Victoria is currently in a transport construction boom with 29 major road and rail projects being built.

Victoria's Big Build website provides information about travel disruptions for the major projects.

For more information, visit bigbuild.vic.gov.au/about

Project timeline

DatePhase

October 2016

Foundation works to strengthen the ground commenced.

Removal of Clayton Station

April 2017

First piers installed

First beams installed

June 2017

Foundation works completed

Clayton Station design released

July 2017

Twin track piers installed at Centre Road

Haunches installed

August 2017

Installation of parapets commenced

Beams installed over Clayton Road

September 2017

Construction on Clayton Station

Platform commenced

October 2017

All piers installed

Beams installed over Centre Road

November 2017

100 per cent of beams installed

December 2017

Embankment construction started

March 2018

100 per cent of new track laid

Commence installation of rail signalling

Early 2018

Clayton Station operational

Track and signalling complete

Clayton and Centre roads level crossings removed

Mid to late 2018

Open space landscaping complete

Bicycle and pedestrian path complete

Walking tours – back by popular demand

We were thrilled with the overwhelming interest in our Caulfield to Dandenong walking tours in January and February.

We want to make sure that everyone who is interested in these tours doesn’t miss out, so we’ve started an online register where you can express your interest in advance.

How do I register for future tours?

Email your name, phone number and which areas of the project you would be interested in seeing to contact@levelcrossings.vic.gov.au

Once enough people have registered interest, we will be in contact with the details of the next tour.

View the print PDF of this community update PDF, 492.6 KB

Was this page helpful?
Send feedback

SMS updates

Receive SMS on the progress of the Level Crossing Removal Project

Sign up for SMS updates

Updates

Stay up to date with the progress of the Level Crossing Removal Project

Sign up for updates

Contact Us

1800 105 105

Get in touch with us for any queries you have about our projects

24 hours, 7 days