24 May 2018

Five crossings gone, four to go

Trains running on elevated rail along the CTD line

Construction works are well on track to remove level crossings, build new stations and create new open space on the Cranbourne – Pakenham line.

The Caulfield to Dandenong Level Crossing Removal Project will not only relieve significant traffic congestion, and improve safety for road and rail users, but will allow more trains to run on Melbourne’s busiest rail corridor.

The nine level crossings being removed before the end of 2018:

Level crossings removed:

  • Clayton Road, Clayton
  • Centre Road, Clayton
  • Corrigan Road, Noble Park
  • Heatherton Road, Noble Park
  • Chandler Road, Noble Park

Level crossings removal in progress:

  • Grange Road, Carnegie
  • Koornang Road, Carnegie
  • Murrumbeena Road, Murrumbeena
  • Poath Road, Hughesdale

Straddle carrier bids farewell

As we say our final goodbye to the gantry cranes and straddle carrier at Murrumbeena, we have a look back at everything they have helped us achieve.

Over the 180 days the straddle carrier was operating, it travelled more than 260 kilometres back and forth along the rail line as it installed 174 concrete beams between Caulfield and Hughesdale, each weighing up to 420 tonnes.

The gantry cranes have now been taken down and the straddle carrier is being decommissioned at ground level in Murrumbeena. With this phase complete, the construction team in this area have shifted their focus to installing the new tracks on the structure as we get closer to removing the four remaining level crossings between Caulfield and Dandenong.

Straddle carrier at CTD in construction

Trader News

A dedicated trader team have been engaging directly with local businesses over the course of the project on a range of initiatives that provides support to traders.

Recently our dedicated trader team were out in Hughesdale with the vibrant group of traders, located either side of the level crossing along Poath Road. Together they initiated a family-focused street festival that will hopefully become an annual event in Hughesdale. A number of traders got involved with footpath stalls and special offers for the local community. Community members turned up in support of their local traders enjoying the free entertainment, giveaways, and discovered the best these local traders had to offer.

"The event was uplifting. I haven't seen so many people on the street at the same time. We got closer to the community and they got closer to us." – Mousa from Knafeh Nabulseyeh

"Being a new business to Poath Road we were delighted with the number of people who came into our store and so warmly welcomed us." – Julie, Total Dance Australia

Project timeline

Key construction milestones

DateProgress

October 2016

  • Piling (ground strengthening) commenced

January 2017

  • First pier installed between Carnegie and Hughesdale
  • Gantry crane arrives

Feb – May 2017

  • First pier installed at Clayton and Noble Park
  • Cranes commence lifting beams and deck segments onto support piers at Clayton and Noble Park

June – Sept 2017

  • Carrier system operational between Murrumbeena Station and Grange Road
  • Piling complete at Carnegie, Murrumbeena, Clayton and Noble Park

Late 2017

  • All piers and beams installed at Noble Park
  • Piling complete Hughesdale

2018

  • Rail laid on elevated deck
  • Ground level buildings installed
  • Retaining walls complete
  • Overhead wiring complete
  • Rail line operating on elevated structure
  • New stations open at Carnegie, Murrumbeena, Hughesdale, Clayton and Noble Park
  • Bicycle and pedestrian path complete
  • Open space landscaping complete
  • All level crossings removed

2 more crossings gone forever

The dangerous and congested level crossings at Clayton Road and Centre Road in Clayton are gone forever.

Before these level crossings were removed, they were a source of pain and frustration for the local community. The boom gates at these crossings were down for up to 82 minutes during the morning peak periods, significantly affecting travel times and causing congestion for over 18,000 motorists who use these roads daily. Removing these level crossings will also provide safer and easier access to Clayton Station and the local traders.

The crossings were removed during the autumn construction blitz which saw our team complete signalling works, overhead wiring installation and tie in the elevated structure to the existing rail line through abutments. The brand new Clayton Station was also opened to the public with our team working around the clock on the station platforms, concourse, forecourt and building.

"To see it finally happen, it's marvellous. I know as a driver I have to wait quite some time to get through the level crossing to go to the shops, schools and doctors. It's a great improvement, not just for now, but also for the next 100 years. It hasn't been built just for now, it has been built for the future." – Gayle, local resident

Students uphold Clayton's heritage

In October 2016, we salvaged the Clayton Station heritage listed shelter so that it could be refurbished and reinstated into the new Clayton Station precinct.

Last month we handed over the building to Chisholm TAFE to undertake refurbishment of the building as part of its students' curriculum. The complex project involves students across a variety of trades, including carpentry and electrical, working on the refurbishment under the guidance of a Victorian Heritage Advisor.

Some of the works will include repainting the shelter, installing new floors, windows, roofing and redoing the electrical work. The shelter will feature an internal wall display about the old railway at Clayton.

Jobs for apprentices, trainees and cadets

The Level Crossing Removal Project is creating hundreds of opportunities for apprentices, trainees and cadets.

The Major Projects Skills Guarantee requires contractors on projects worth more than $20 million to ensure at least 10 per cent of their workforce is made up of apprentices, trainees and engineering cadets. Currently, our engineering cadets, apprentices and trainees working on the rail have done a total of 171,561 hours on the Caulfield to Dandenong project so far – that’s equivalent to 98 full time employees.

Cadets undertake a Graduate Diploma in Railway Signalling coupled with various workplace rotations within the partner companies involved in the program.

‘’I’m utterly proud to have joined the wave of railway signalling cadets. I will have the chance to leave a legacy by being involved on the Caulfield to Dandenong Level Crossing Removal Project.’

– Christelle, Railway Signalling Engineering Cadet

LXRA worker on CTD

View this in PDF format PDF, 861.0 KB

View this PDF in Greek PDF, 874.5 KB

View this PDF in Italian PDF, 859.3 KB

View this PDF in Punjabi PDF, 941.2 KB

View this PDF in Vietnamese PDF, 1.4 MB

View this PDF in Traditional Chinese PDF, 949.1 KB

View this PDF in Simplified Chinese PDF, 941.8 KB

View this PDF in Khmer PDF, 1021.4 KB

Was this page helpful?
Send feedback

SMS updates

Receive SMS on the progress of the Level Crossing Removal Project

Sign up for SMS updates

Updates

Stay up to date with the progress of the Level Crossing Removal Project

Sign up for updates

Contact Us

1800 105 105

Get in touch with us for any queries you have about our projects

24 hours, 7 days