Caulfield to Dandenong - Area 1 update: May 2018

29 May 2018

What we’ve been doing

Major works are underway to remove dangerous level crossings at Grange, Koornang, Murrumbeena and Poath roads and build brand new stations in Carnegie, Murrumbeena and Hughesdale. Now that all the spans between Caulfield and Hughesdale have been installed, we have demobilised the gantry cranes, straddle carrier and support beams from the assembly area in Murrumbeena.

You may have noticed that we have been ramping up works on the brand new stations, with the last piece of canopy now installed at Murrumbeena Station. We are continuing the canopy installation in Carnegie and the first pieces have been installed in Hughesdale.

Works are continuing on the ground level buildings at Murrumbeena and Carnegie stations, and the slabs for the buildings at the brand new Hughesdale Station have been laid. Other station works being undertaken at Hughesdale include the completion of the hollow core deck.

Track installation is progressing through in Carnegie and Murrumbeena and construction of the retaining walls in Hughesdale. These walls will tie in the existing tracks with the new elevated structure. Overhead wiring masts are being installed through in Carnegie and the first lengths of overhead wiring are in place.

What’s coming up

In the coming weeks the remaining sections of the Carnegie Station canopy will be installed and we will continue station platform works in both Murrumbeena, Carnegie and Hughesdale as well as installation of new track. While trains are not running in early June the removal of old ballast, track and overhead wiring along the corridor will begin to prepare for the new parkland which will be completed by the end of the year.

Caulfield to Dandenong canopy under construction

Upcoming disruptions

Road

To maintain safety in Murrumbeena for truck movements, Neerim Road, Murrumbeena will require traffic management until late May 2018. Two-way traffic will be maintained. There will also be intermittent traffic management on Lorne Street, Girdwood Avenue, and Dandenong Service Road, Carnegie and Railway Parade, Hughesdale. Local access will be maintained.

Rail

Buses will replace trains:

  • From 8:00pm Monday 21 May until last service Wednesday 23 May between Caulfield and Westall
  • From 12:30am Saturday 26 May until last service Sunday 27 May between Caulfield and Dandenong
  • From 8:00pm Tuesday 29 May to 8:00pm Friday 1 June between Caulfield and Westall
  • From 8:00pm Friday 1 to Saturday 2 June between Flinders Street, Westall and Moorabbin (Frankston Line)
  • From Sunday 3 to last service Friday 8 June between Caulfield and Westall
  • From Saturday 9 to last service Monday 11 June between Flinders Street, Westall and Moorabbin (Frankston Line)
  • From Tuesday 12 to last service Sunday 17 June between Caulfield and Westall

Project timeline

DateProgress
October 2016
  • Foundation works to strengthen the ground commenced
January 2017
  • First pier installed between Carnegie and Hughesdale.
  • Gantry crane arrives
February 2017
  • First horizontal span installed by the gantry cranes
June 2017
  • Platform works commenced
July 2017
  • Straddle carrier arrives to site and is assembled
  • Assembly of two 94-metre support beams
August 2017
  • Straddle carrier commenced operation
September 2017
  • Horizontal spans installed across Murrumbeena Rd
October 2017
  • Hughesdale Station demolished
November – December 2017
  • 100 horizontal spans installed, including across Koornang Road
  • Carnegie platform works commenced
Early 2018
  • All foundation works to strengthen the ground complete.
  • All piers installed.
  • Horizontal spans installed across Grange and Poath Roads.
  • Hughesdale Station Platform works commence.
  • Commence laying elevated track.
  • Rail signal installation.
Mid – late 2018
  • Grange, Koornang, Murrumbeena and Poath Road level crossings removed.
  • Track and signalling complete.
  • Open space landscaping complete.
  • New stations open at Carnegie, Murrumbeena and Hughesdale.
  • Bicycle and pedestrian path complete.

View this is PDF format PDF, 350.0 KB

Was this page helpful?
Send feedback

SMS updates

Receive SMS on the progress of the Level Crossing Removal Project

Sign up for SMS updates

Updates

Stay up to date with the progress of the Level Crossing Removal Project

Sign up for updates