Skip to main content

Mooroolbark multi-deck car park has its first level

30 Mar 2021

The new multi-deck car park at Mooroolbark is now taking shape, with the first-floor slab now in place.

The slab, containing nearly 300 cubic metres of concrete, was poured this week, marking a major milestone for the project.

Construction has been flying, starting with foundation work completed in January and the support columns for this first floor going in earlier this month.

If you’d like to learn more about the construction of the car park, or the Manchester Road level crossing removal, sign up for one of our site tours, where our people will take you behind the scenes on this major infrastructure project.

This car park is part of the Manchester Road Level Crossing Removal Project and will double parking to 900 spaces.

The car park will be completed in 2022.