All the latest on Buckley

30 Oct 2018

We’ve removed the dangerous and congested level crossing at Buckley Street, Essendon, months ahead of schedule.

Last month the new Buckley Street road underpass opened to vehicles.

The new underpass has two lanes travelling east towards Mt Alexander Road and one lane travelling west.

A dedicated service road on Buckley Street, connecting Russell Street to Mt Alexander Road, has its own traffic light sequence to make sure cars and buses move safely and easily through the intersection. The works on the service roads are complete and Sherbourne Street has become two-way.

Pedestrian underpass upgrades

We’re completing work on the Essendon Station central underpass which is due to reopen in the coming weeks. The underpass will have two new Disability Discrimination Act 1992 compliant ramps, as well as stairs, leading up to Russell and Rose streets.

The southern underpass has been given a facelift with new stairs and walls returned to their original heritage red brick finish. Upgrades to the northern underpass will begin in November and it will then be available for cyclists to use as a link between Rose and Russell streets.

Crowds at the Buckley Street underpass

Local business profile

Get moving with Bodywise Myotherapy and Pilates

Did you know that you can get injured just by sitting still? Since their beginnings in 2014, the team at Bodywise Myotherapy and Pilates have treated a range of musculoskeletal conditions – including those associated with physical inactivity. Bodywise co-owner, Daniel McKay, says Australians aren’t
moving enough.

spend an average of 22 hours a weeksitting, not even including the time spent commuting to and from their place of work. While the team at Bodywise treat a range of patients from professional sports people through to weekend warriors. Daniel says they have seen an increase in office workers visiting the clinic because of pain associated with leading a relatively sedentary lifestyle.

“It’s not just office workers, as university and high school students are also at risk because of long periods of time studying while seated at a desk.”

Bodywise Myotherapy and Pilates has a highly experienced team ready to help keep your body in its most optimal state of health and wellbeing. Additionally, you can follow ‘Blogywise’ on their website for the latest in health and fitness insights from Daniel, Ashlee, Alex and Julie. So, contact the Bodywise
team today to get moving, and moving better than you have before!

Contact details

Address: 125 Buckley Street, Essendon

Phone: 8597 0085

Email: info@bodywisemyotherapy.com

Website: bodywisemyotherapyandpilates.com

What happens next?

We will be monitoring how local streets are used over the next few months. This monitoring will include site inspections, survey of traffic movements and traffic counts to determine if any additional traffic management measures are required, in consultation with the relevant authorities.

We'll also be continuing work on the Russell and Rose streets central underpass entrances until mid-November. And once those works are complete we'll be beginning works on the northern pedestrian underpass upgrade.

Buses will return to Russell Street on Sunday 11 November and bus shelters will be installed on Rose and Buckley streets. There will be minor disruptions to roads and footpaths as we continue landscaping and finishing works.

School girls singing at the Buckley Street underpass opening

New cycling routes for Essendon

Before work began to remove the Buckley Street level crossing, we gathered feedback from Moonee Valley City Council, VicRoads and technical transport specialists to help us create better connections to local cycling routes and to the Essendon Station precinct.

A designated Strategic Cycling Corridor is proposed north of the level crossing – to include Miller, Shamrock and Fletcher streets – moving cyclists away from Buckley Street and on to existing designated cycling connections, like Mt Alexander Road.

In 2019, we are creating a new, signalised intersection at Mt Alexander Road and Shamrock Street, enhancing the corridor by providing a safer east-west cycling route, connecting to cycling infrastructure. New bicycle lane markings, or sharrows, on some local roads will help direct riders to the nearby
strategic cycling corridors.

Project timeline

Date Progress

June 2018

  • Piling work start
  • Major services relocation
  • Drainage works in Russell Street

July 2018

  • Installation of permanent barriers
  • along service road
  • Construction of service roads
  • Relocation of Protective Services
  • Officers' building
  • Start of station underpass works

August 2018

  • Boom gates removed
  • Construction of road bridge
  • Station underpass work
  • Excavation of the road underpass

September 2018

  • Excavation of the road underpass
  • Construction of rail bridge
  • Installation of architectural
  • panels on the underpass
  • Station underpass works
  • Landscaping

October – December 2018

  • Minor road works
  • Landscaping
  • Station underpass works
  • Traffic monitoring

Early 2019

  • Traffic monitoring
  • Level Crossing Removal works completed
  • Works begin for Shamrock Street - Mt Alexander Road intersection signalisation

View the print PDF version of this community update PDF, 816.3 KB