Carnegie Station closure

23 Jan 2017 to 13 Mar 2017

Category: rail

Carnegie Station will temporarily close from 1:00am Monday 23 January until 4:00am Monday 13 March 2017.

Train replacement buses will operate between Caulfield and Murrumbeena stations, stopping at Carnegie Station. 

Click below for more detailed information.

Carnegie Station will temporarily close from 1:00am Monday 23 January until 4:00am Monday 13 March 2017 to construct piles and pile caps on the station platforms and begin construction of the elevated rail and the new station.

Initially the plan was to close the station for eight weeks from 16 January to safely undertake these works. A review of the construction program has enabled the closure period to be reduced to seven weeks.

Train replacement bus services will operate during the station closure. Customers for Carnegie Station are encouraged to change at Caulfield and Murrumbeena stations to board the train replacement bus to Carnegie Station.

Customers should allow up to 15 minutes' extra travel time.

For full train replacement bus service timetables, please see the PTV website.

For a full list of train replacement bus locations please view the list below:

Station

From City

To city

Caulfield

Bus stop – service to Carnegie Station

Normanby Road

Exit Caulfield Station on to Normanby Road. Turn right and proceed to bus stop.

Bus stop termination point

Normanby Road

Carnegie

Bus stop – service to Murrumbeena Station

1113 Dandenong Road

From Carnegie Station walk on Woorayl Street towards Koornang Road, turn right onto Koornang Road, cross Dandenong Rd and turn right

Bus stop – service to Caulfield Station

1076 Dandenong Road – From Carnegie Station, walk north along Koornang Road for approximately 190 metres, turn left at Dandenong Road and proceed to the train replacement bus stop.

Murrumbeena

Bus stop termination point

463 Neerim Road

Bus stop – service to Carnegie Station

463 Neerim Road – from Murrumbeena Station, walk north along Murrumbeena Road for approximately 20 metres, turn right at Neerim Road and proceed to the train replacement bus stop.

Sunbury line

8 Mar 2017 to 13 Mar 2017

Category: rail

Buses will replace trains between Sunshine and Sunbury from 8 March to 13 March 2017 while track drainage works on the St Albans Level Crossing Removal Project are undertaken.

Normal services will resume on 14 March 2017.

Click below for more detailed information.

Metro customers

To allow works for the Furlong Main Level Crossing Removal Project to be carried out safely, there will be disruptions to train services on the Sunbury line from first service Wednesday 8 March to last service Monday 13 March 2017. Normal services will resume on 14 March 2017.

Buses will replace trains on the Sunbury line between Sunbury and Sunshine, including some express, limited express and stopping all stations services, to help make customers journey as direct as possible.

Customers should allow up to 45 minutes extra travel time. Please see the PTV website for detailed information.

V/Line customers

Weekdays: Wednesday 8 March to Friday 10 March and Monday 13 March 2017

Trains will run between Gisborne and Bendigo/Echuca. Coaches will replace trains between Southern Cross and Gisborne.

Trains will run between Bendigo and Swan Hill. Coaches will replace trains between Bendigo and Southern Cross Station.

Weekend: Saturday 11 March and Sunday 12 March 2017

Trains will operate between Bendigo and Swan Hill/Echuca. Coaches will replace trains between Bendigo and Southern Cross Station.

Customers should allow an extra 60 minutes travel time on Saturday and Sunday. On weekdays, customers are advised to allow an extra 40 minutes travel time.

During these works, buses will replace Night Network trains on the Sunbury line every hour on Friday (Saturday morning) and Saturday (Sunday morning) nights.

  • Train replacement buses will meet Night Network trains at the connecting stations.
  • Signage will be displayed around the station precinct directing customers to train replacement bus stop locations.
  • During the disruptions, pedestrian detours may be in place around St Albans and Ginifer stations. Please follow the instructions of signage and traffic controllers at all times.

Please see the V/Line website for detailed information.

Sydenham Road closure

22 Feb 2017 to late-2018

Category: road

Sydenham Road will be closed at Melton Highway from 22 February to late-2018. 

Access to Sydenham Road from Melton Highway will be via Overton Lea Boulevard and Trickey Avenue. 

Click below for more detailed information.

Pedestrian access will be maintained at all times.

Access for residents and businesses will be maintained. 

Please observe local traffic signs and detour routes.

Belgrave/Lilydale lines

3 Mar 2017 to 5 Mar 2017

Category: rail

To enable works associated with the Blackburn/Heatherdale and Bayswater Level Crossing Removal Projects, the following disruptions to train services are planned:

From 8:45pm Friday 3 until 8pm Saturday 4 March 2017 buses will replace trains between Box Hill and Ringwood stations.

From 8:00pm Saturday 4 March until the last service on Sunday 5 March 2017 buses will replace trains between Box Hill and Belgrave stations.

Click below for more detailed information.

Normal services will resume on 6 March 2017.

Customers should allow up to 30 minutes' extra travel time.

Blackburn pedestrian access

3 Mar 2017 to 5 Mar 2017

Category: pedestrian

To enable access and drainage work the Blackburn Station underpass will be closed. Additionally the pedestrian crossings at Cottage Street and Oliver Avenue will close while we carry out works on overhead rail structures.

Access across the rail line will be available at Blackburn Road.