Construction has started on the removal of the Main Road and Furlong Road level crossings with both projects to be completed by mid 2017. Construction at both sites is expected to take 12 to 18 months to complete.

A project team including CPB Contractors, Aurecon, Arcadis, VicRoads, Public Transport Victoria and Metro Trains Melbourne will remove the level crossings and rebuild Ginifer and St Albans Stations. The project will also remove level crossings at Blackburn Road in Blackburn and Heatherdale Road in Mitcham.

Design

Furlong Road, St Albans

This level crossing removal will include:

  • lowering the rail line below Furlong Road
  • moving Ginifer Station up to the intersection at Furlong Road, with access to the station at Furlong Road and Bond Street
  • installing platforms in the rail cutting accessed via lifts, ramp and stairs
  • building a walking and cycling path parallel to the rail line, from Furlong Road to Willis Street
  • relocating the car park to the east of the rail line, maintaining at least the same number of spaces.

Ginifer Station artist impression

Artist impression of Ginifer Station.

Main Road, St Albans

Removal of the Main Road level crossing will transform the station area into a modern transport interchange. The design includes:

  • lowering the rail line below Main Road
  • rebuilding St Albans Station
  • accessing lowered platforms via lifts, ramps and stairs
  • reconstructing the station car park providing the same number of spaces as a minimum
  • building a walking and cycling path
  • relocating the bus interchange from Alfrieda Street to either side of the station
  • a pedestrian overpass at Ruth Street.

Main Road level crossing artist impression

Artist impression of the Main Road level crossing removal.

The video below shows an overview of the 50 level crossings that will be removed, including designs for the removals at Furlong Main Blackburn Heatherdale.

Planned travel disruptions

Careful planning and scheduling will maintain road access and train services through much of the construction program, however some road, rail and station closures will be necessary to undertake works safely. 

View planned travel disruptions page

Construction

As part of major construction on the Main Road Level Crossing Removal Project, works took place at Main Road St Albans during January 2016. The level crossing was closed for 19 days to enable the construction of a bridge deck directly to the west of the existing level crossing.

The bridge deck allows traffic to flow on Main Road while the construction team continues to dig underneath. This technique significantly reduces traffic impacts during construction.

In addition to continuing works at Main Road in St Albans, works are also progressing at Furlong Road.  In January the team worked approximately 2,800 man hours to:

  • demolish sections of the station buildings and install hoarding on platform two
  • install overhead structures
  • construct retaining walls to build the new Ginifer Station concourse and Mulhall Drive pedestrian bridge
  • begin trenching works along the rail track and Kingsley Street to the M80 Ring Road St Albans
  • excavate and start works for the new station foundations

There were also works in mid-February to continue the foundation works for the new station.

Impacts

Delivering the Main Road and Furlong Road level crossings removal projects together will accelerate the delivery of the overall level crossing removal project, minimise disruption to residents and road users, and reduce the number of closures required on the Sunbury rail line. We are dedicated to minimising the impacts on the community as much as possible; however, construction of a major project does have some unavoidable impacts.

Due to this construction there are changes to train and bus services, station parking and to traffic and pedestrian access in St Albans. There will also be noise, dust and vibration and night works are required so we can work on the train line when services are not running. We will work with local traders and residents to minimise impact of construction as much as we can.

Car park changes at St Albans Station

Monday 29 February 2016 to Mid 2017

As part of the works to remove the level crossing at Main Road there will be long term car space closures around the station.

  • Up to 106 car spaces closed in the West Esplanade car park for excavation to lower the rail line
  • Alternative parking will be provided in the St Albans Hotel and St Albans Bingo Centre car park on McKenchnie Street

Car park changes at Ginifer Station

Thursday 24 March 2016 – Mid 2017

As part of the works to remove the level crossing at Furlong Road there will be long term car space closures at the Willaton Street car park.

  • Alternative parking will be provided in the St Albans Road car park and at the rear of the St Albans Hotel and Bingo Centre car park (1.7 kilometres from Ginifer Station and will take approximately five minutes to drive).
  • Customers are encouraged to consider alternative transport to the station during this time, where possible.

Community

The final design for the Furlong Road Level Crossing Removal project will be developed with input from the local community - including residents, traders and community groups - and other key stakeholders like Brimbank Council.

Stay updated

Local residents, businesses and other stakeholders are being kept up to date with the project and its progress via website updates, regular bulletins and letterbox drops, local newspaper advertising, onsite information boards and community information displays.

Sign up for project updates

Publications

Furlong Main Community Update - June 2015 PDF, 1.3 MB

Furlong Main Community Update - September 2015 PDF, 1.1 MB

Furlong Main Community Update - December 2015

Furlong Main Community Update - February 2016

Furlong Main Community Update - April 2016

Map